FILMPORT – PHASE I COMPLEX

Developer: Toronto Film Studios Inc. | Architect: Quadrangle Architects Limited

The project site, on the south side of Commissioners Street, at the east side of the Don Roadway, borders on a shipping channel of Lake Ontario, and has been planned to accommodate more than thirty sound stages.

The structural steel superstructure of each building is somewhat different, however, the stages all have long spans ranging from 23.7 metres to 56.3 metres.  The one thing that they all have in common is the ground floor slabs.  To overcome the very poor soil conditions, the ground floor slabs were all designed and constructed as 250 mm thick flat slabs with 250 mm deep drop panels designed to sustain a live load of 12 kilonewtons per square metre (250 pounds per square foot).  The bay sizes for the flat slabs, at the ground level, are in the range of 6.5 to 7.5 metres, with the drop panels, supported on structural steel “H” piles, which were driven to refusal into shale bedrock.

The shop buildings 8A & 8B have flat roofs with 38 mm deep by 0.76 mm steel deck, supported on, 900 mm deep, long span steel joists.  To attenuate exterior sounds, the roof of the stages have 100 mm of concrete over 50 mm deep composite steel deck resulting in a total concrete thickness of 150 mm.  With the exception of stage 4, the roofs are basically flat with the concrete decks being supported on, 2400 mm deep, long span steel joists, spaced at approximately 1.91 metres centre-to-centre.

All of the buildings’ columns are supported on caissons and/or structural steel “H” piles, socketed or driven to refusal into shale bedrock.  Stage 4 is unique in that, the special buttresses employed to provide lateral resistance and support the barrel arched beams (trusses) of the roof had, in most instances, to be tied down with two, 46 mm diameter Dywidag rock anchors, grouted into the shale bedrock and stressed to a working load of 1000 kilonewtons (225,000 pounds).

In addition to the unique buttresses, supported on reinforced concrete plinths, bearing on caisson caps the roof with a clear span of 56.3 metres is worthy of note.  The arched beams, support, typically 460 mm deep, structural steel wide flange beams at 6.095 metres centre-to-centre, which in turn support 400 mm deep open web steel joist at 1.6 metres centre-to-centre, curved in the vertical plane to create the circular profile of the framing and support the 150 mm thick concrete and composite steel deck roof.

In order to provide the necessary noise attenuation, and to present a uniform appearance, all of the sound stages are clad with textured precast concrete panels supported on perimeter reinforced concrete grade beams spanning between caissons.

By Dave 06 May, 2011
This multi purpose project, located in Toronto, at the north-west corner of King and John Streets is home to the Toronto International Film Festival which has its offices on the fourth, fifth and sixth floors...
By Dave 04 May, 2011
This world class residential condominium, with retail spaces on the first and second levels, is located at the south-east corner of Yonge and Bloor Streets close to Toronto’s fashionable shopping district.
By Dave 03 May, 2011
This multi purpose project, located in Toronto, at the north-west corner of King and John Streets is home to the Toronto International Film Festival which has its offices on the fourth, fifth and sixth floors...
By Dave 02 May, 2011
This sixty-two storey, residential, condominium is constructed over three basement levels, at the north-east corner of the intersection of Yonge Street and The Esplanade.
By Dave 02 May, 2011
This condominium lofts residence is comprised of three components, in a former industrial area of the City of Toronto, west of the downtown, which is being revitalized as a residential community.
By Dave 30 Apr, 2011
The project, consisting of two high-rise residential condominium towers, and future office tower, is located on the west side of York Street, between Brenner Boulevard and Gardiner/Lakeshore Boulevard.
By Dave 29 Apr, 2011
The first phase of this residential condominium project, composed of a twelve storey block and a fourteen storey block, linked by a three storey space bridge truss component, containing three levels of condominium residences...
By Dave 28 Apr, 2011
This four storey up scale condominium, designed to resemble a palatial French chateau, is located at the south-east corner of Bayview Avenue and Post Road, in Toronto.
By Dave 27 Apr, 2011
This residential complex, composed of three, three storey townhouse blocks, with private elevators, and roof terraces, a forty-six storey west tower, and a fifty-six storey east tower is located at the west side of Bay Street...
By Dave 26 Apr, 2011
This condominium project, located at the south-east corner of the intersection of Mill and Parliament Streets, in the redeveloping distillery district of Toronto, is comprised of a nine storey podium...