PIER 27

Developer: Cityzen Development Group
Architect: Architects Alliance

The first phase of this residential condominium project, composed of a twelve storey block and a fourteen storey block, linked by a three storey space bridge truss component, containing three levels of condominium residences, is located on the south side of Queen’s Quay Boulevard East, east of Yonge Street, adjacent to the waters of the Toronto Harbour.

The superstructures and the ground floor landscaped plaza, between the two blocks, are constructed over a four level subgrade parking garage.

Since the project is located in very close proximity to the shores of Lake Ontario, the entire site is enclosed by a continuous perimeter caisson wall, incorporating 915 mm diameter caissons, to facilitate the excavation for both phases 1 and 2, and control the ground water conditions. The footings below the walls and columns are both strip and spread type and bear on natural undisturbed soil capable of safely sustaining a pressure of 2500 kilopascals, (i.e. 52,200 pounds or 26.1 tons per square foot).

The subgrade parking level slabs are typically constructed as 200 mm thick reinforced concrete flat slabs, with 125 mm deep drop panels over the columns. The ground floor slab below the landscaped area is typically a 250 mm thick reinforced concrete flat slab, with 150 mm deep drop panels and 300 mm deep capitals over the columns.

In the west block, the floor slabs are typically 200 mm thick, one-way reinforced concrete slabs spanning between the reinforced concrete shear walls at 6.7 metres on center. Similarly, in the east block, the slabs are the same 200 mm thickness, in the south half, where the reinforced concrete shear walls are at 6.6 metres on center, but in the north half where the reinforced concrete shear walls are spaced at 7.4 metres, the slabs are increased to a thickness of 210 mm.

Spanning between the elevator core, at the north end of the twelfth floor, of the west block, and the stairwell area, at the relative middle of the twelfth floor, of the east block, there is a three storey bridge truss containing three levels of residential condominium units. The three level bridge is in excess of 12.0 metres high by 12.0 metres wide. Within the span, arranged in the party partitions, between suites, there are two vertical brace frame systems incorporating HSS 203x152x9.5 tubular sections, to act as vertical diaphragms, within the tunnel like structure of the bridge. To resist lateral forces, before the roof and floors are cast, to act as diaphragm plates, diagonal bracing, in the form of two 152x89x7.9 angles has been installed below the roof and floor concrete on composite steel decks. The 100 mm thick concrete on 51 mm deep by 0.91 mm thick composite steel deck, of the floors, and 0.76 mm thick composite steel deck of the roof are supported on W460x74 purlins at the twelfth floor level, W460x68 purlins at the thirteenth, and fourteenth floor levels and by W460x52 structural steel purlins at the roof level.

By Dave 06 May, 2011
This multi purpose project, located in Toronto, at the north-west corner of King and John Streets is home to the Toronto International Film Festival which has its offices on the fourth, fifth and sixth floors...
By Dave 04 May, 2011
This world class residential condominium, with retail spaces on the first and second levels, is located at the south-east corner of Yonge and Bloor Streets close to Toronto’s fashionable shopping district.
By Dave 03 May, 2011
This multi purpose project, located in Toronto, at the north-west corner of King and John Streets is home to the Toronto International Film Festival which has its offices on the fourth, fifth and sixth floors...
By Dave 02 May, 2011
This sixty-two storey, residential, condominium is constructed over three basement levels, at the north-east corner of the intersection of Yonge Street and The Esplanade.
By Dave 02 May, 2011
This condominium lofts residence is comprised of three components, in a former industrial area of the City of Toronto, west of the downtown, which is being revitalized as a residential community.
By Dave 30 Apr, 2011
The project, consisting of two high-rise residential condominium towers, and future office tower, is located on the west side of York Street, between Brenner Boulevard and Gardiner/Lakeshore Boulevard.
By Dave 28 Apr, 2011
This four storey up scale condominium, designed to resemble a palatial French chateau, is located at the south-east corner of Bayview Avenue and Post Road, in Toronto.
By Dave 27 Apr, 2011
This residential complex, composed of three, three storey townhouse blocks, with private elevators, and roof terraces, a forty-six storey west tower, and a fifty-six storey east tower is located at the west side of Bay Street...
By Dave 26 Apr, 2011
This condominium project, located at the south-east corner of the intersection of Mill and Parliament Streets, in the redeveloping distillery district of Toronto, is comprised of a nine storey podium...
By Dave 25 Apr, 2011
This thirty-nine storey residential condominium structure with retail spaces at the ground floor is located at 390 Cherry Street, north of the railway lines.
More Posts
Share by: